WHAT ARE THE THEORETICAL STAGES OF SHIPBUILDING
Because complex ships are typically one-off orders built in very short series, a significant amount of engineering work must be performed for each new project. It is important to recognize that even throughout these engineering or even acquisition stages the planning is already setup and refined with more detail. Such as the master document list to account for specific timelines and steps that together complete the required documents and input. For this paragraph input and text is used from Rose, C. (2017). Atomatic production planning for the construction of complex ships.
Basic design
During this stage, the ship is described as a total system. An initial solution is specified through creating a preliminary general arrangement and selecting the materials and technologies to be used (hull form, propulsion systems, mission equipment, etc.). This stage is also referred to as conceptual or preliminary design.
Functional design
Each of a ship’s systems are schematically defined during this design stage. These diagrams are used to create required material lists for each system and to acquire owner and regulatory approval.
Transition design
During this stage, a ship’s design is reorganized from system schematics to a design based on physical location (such a sections, blocks, zones, etc.). The purpose of transitional design is to make the function design suitable for work instruction design.
Work instruction design
This stage makes the ship design suitable for production. This is accomplished by determining the arrangements, dimensions, and other specifications of all individual parts. Detailed cost estimations and construction drawings are produced during this design stage.
This stage is also combined with transition design to form a single stage referred to as detail design or engineering.
Production
The purpose of production is to build the ship design created during the engineering stages. Production stages are divided into two groups: those related to constructing a ship’s hull and those related to outfitting. The following hull-related stages are included in the shipbuilding process.
Panel construction
Panels are produced during this stage, where a typical panel is composed of several steel plates butt-welded together stiffened by profiles, girders and brackets.
Section assembly
During section assembly, sections are built by welding together panels and individual parts. A section is the basic construction unit of a ship, where a typical complex ship is composed of 50-200 sections.
Block building
In some cases, several sections are welded together to form blocks prior to erection.
Erection
This stage involves assembling the sections and blocks of a ship on a slipway/drydock to form the hull. The sections and blocks are then welded together during erection.
Launching
During this stage the ship is moved from the slipway to the quay. The hull must be watertight prior to launching, and all external underwater work should be completed. The shipbuilding process contains the following outfitting-related stages.
Pre-outfitting
Components are mounted to sections in the section assembly area during the pre-outfitting stage. This is done while the sections are still being assembled or after section assembly is complete prior to painting the section.
Painting
After a section is assembled and the necessary pre-outfitting is completed, the section is moved to a paint hall to be painted.
Slipway outfitting
Components are installed in the partially-erected ship on the slipway during this stage. It is only possible to use a crane to assist with installing large items while the section composing the ceiling of the room containing the item has not yet been erected.
Quay outfitting
This stage involves installing components in the ship while the ship is moored alongside the quay. At the conclusion of this stage, all components should be installed.
Shipyard Planning in Practice
Master plan
The Master Plan is created at a very early stage in a project, during basic design. This plan is typically produced prior to contract signing. The Master Plan contains:
- Erection Plan
- Section Building Plan
- Outfitting Plan
The completion dates of key milestones in the shipbuilding project, such as contract signing, keel laying, launching, and delivery are also included in this plan. These milestones are included in the contract, and payments from the owner to the yard are associated with their completion. This plan also indicates how a shipbuilding project interacts with the previous and following project in terms of global shipyard resource requirements. Because the Master Plan is created early in the engineering process, a shipyard works with a fairly limited ship design when making this plan. Therefore, a shipyard relies on historical data, estimation methods, and expert judgment to create the Master Plan.
Erection plan
The second planning level is the creation of the Erection Plan. A shipyard generates the Erection Plan sometime during the end of transition design or in the beginning of the work instruction design. This plan determines the time each section is erected on the slipway. The slipway is a strategic resource for European shipyards because it typically limits a shipyard’s throughput. Furthermore, unlike section building, it is not possible to gain additional slipway capacity through outsourcing. A shipyard avoids delaying the Erection Plan whenever possible, as doing so implies the following project will also be delayed.
Section building plan
After the Erection Plan is completed, the shipyard creates the Section Building Plan. This generally occurs at the start of work instruction design. This plan indicates when each section should be assembled and pre-outfitted. The Section Building Plan is generated by extrapolating backwards from the Erection Plan to ensure that each section is ready to be erected on time. The number of sections that can be built simultaneously is limited by the floor area of the section building hall. Whenever the section building requirements of a shipyard exceed its own capacity, the production of entire sections is outsourced. It is also common for shipyards to only consider pre-outfitting on a rudimentary level when creating the Section Building Plan. For example, each section may be assigned two weeks for pre-outfitting regardless of the required outfitting work. For each section the pre-outfitting process is given some overlap with the section assembly process (usually around one week). This allows for the installation of components which are easier to mount before the entire section is fully assembled, such as double bottom pipes. The inputs and outputs of the Section Building Plan are shown in the figure.
The daily operations at a shipyard are recognized through their intense dynamic. As the initial objective of the plan is to mitigate risks the proposed plan should be kept up to date by aligning the various perspectives from all the project participants at the shipyard. This translates into a IT-infrastructure that resembles this average example.
Outfitting plan
A detailed Outfitting Plan on the component level is not created by the shipyard. Instead, the shipyard uses the Section Building Plan to indicate to the subcontractors when each section is available for pre-outfitting. The Erection Plan also contains the time period available for slipway outfitting. Similarly, the painting schedule indicates the latest point in time hotwork can be performed in a space. Subcontractors independently maintain their own schedules. A weekly meeting is conducted with representation from each of the outfitting subcontractors and the shipyard. During these meetings, the subcontractors and shipyard determine what outfitting will be performed during the upcoming week, resolve conflicts between subcontractors, and make minor adjustments to the Section Building Plan
Towards an integrated plan for the shipyard as a whole
Through understated figure it becomes apparent how the various input on the shipyard characteristics, the product hierarchy of the ship and the project timelines are all impacting the setup and contents of the plan.
Unlock the potential of your shipyard with Floor2Plan. Discover how our innovative software can streamline operations and boost productivity.
How to improve predictability in your shipyard
Schedule a meeting
Come to a joint approach with us
Evaluate our prototype in your shipyard
Go-live and improve